Sector: Industrial & Manufacturing

BD Mould Line Replacement

Project Description

SDS were appointed by the client as part of a £7.8 million site wide update, including the repositioning of a process line and an expansion to the existing building

The area of works covered 2,980m2 inside an 8m height manufacturing building

The project consists of multiple phases of works, safely repositioning over 20 moulding machines each weighing between 20 to 2st

A detailed project programme was created to enable construction to take place whilst maintaining production in a clean and safe environment

Electrical enabling works on live switchgear was coordinated with designated shutdown periods

Special consideration for Health and Safety, and futureproofing of systems was incorporated into the design

Specialist fire aspirating system designed to cover all areas for early warning detection. High powered Visual Alarm Devices (VADs) specified for industrial environments with high
background sound levels

High and low voltage transformer upgrades, relocation works and high voltage grading studies.

£7.8m Moulding Line replacement for multi-million pound medical technology company BD