Replacement of two in number primary distribution low voltage panels for the Heavitree and Wonford Hospital sites
Critical service LV distribution panels including integration with an existing emergency standby generator
This was an operationally live hospital environment and risk to staff and patients needed to be consideed throughout the complex installation and change over period
Worked with specialist low voltage panel manufacturers to deliver a bespoke solution minimising downtime for critical power supplies
Produced a multi-phase design to ensure power continuity to critical services including modular installation, and temporary generator provision
To ensure that the installation was carried out in a low manner and to migrate distruption to the client, SDS designed a prefabricated solution
This allowed the project to be carried out with a phased changeoever at weekend and was completed on time and under
budget
Appointed to produce full condition survey, technical design, tender documents and oversee the tender process
Worked with specialist manufacturers